实用英语实用英语实用英语Fidic测试(英文试题)
题目内容

The Contract can be terminated when(  )

2024-07-09

A.the Contractor subcontracts the whole of the Works without the required agreement,

B.the Contractor want,

C.the execution of substantially all the Works in progress is prevented for a continuous period of 84 days by reason of Force Majeure,

D.the Employer substantially fails to perform his obligations under the Contract,