the major difference between pert and cpm networks is:

2024-07-09

A.pert requires three time estimates whereas cpm requires one time estimate.

B.pert is used for construction projects whereas cpm is used for r & d

C.pert addresses only time whereas cpm also includes cost and resource availability.

D.pert requires computer solutions whereas cpm is a manual techniqu

E.E.pert is measured in days whereas cpm uses weeks or months.