● A project manager believes that modifying the scope of the project mayprovide added value service for the customer. The project manager should(75).

2024-07-09

A.assign change tasks to project members

B.call a meeting of the configuration control board

C.change the scope baseline

D.postpone the modification until a separate enhancement project isfunded after this project is completed according to the original baseline