专业技术中级资格系统集成项目管理工程师基础知识2011上半年系统集成项目管理工程师上午试题
题目内容

The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that <u>(74)</u>。

2024-07-09

A.the project is ahead of its planned schedule

B.less work was completed than was planned

C.the cost overrun for work completed

D.the cost under-run of performance to date