●(71)assesses the priority of identified risks using their probability of occurring, thecorresponding impact on project objectives if the risks do occur, as well as other factors suchas the time frame and risk tolerance of the project constraints of cost, schedule, scope, andquality.

2024-07-09

A.Quantitative Risk Analysis

B.Qualitative Risk Analysis

C.Enterprise Environmental Factors

D.Risk Management Plan