61● Project (69) Management includes the processes required to ensure thatthe project includes all the work required, and only the work required, tocomplete the project successfully.
A.Integration
B.Scope
C.Configuration
D.Requirement
开始考试练习点击查看答案62● On some projects, especially ones of smaller scope, activity sequencing,activity resource estimating, activity duration estimating, and (70) are sotightly linked that they are viewed as a single process that can be performedby a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
开始考试练习点击查看答案63● In approximating costs, the estimator considers the possible causes ofvariation of the cost estimates, including(71) .
A.budget
B.plan
C.risk
D.contract
开始考试练习点击查看答案64● Project Quality Management must address the management of the projectand the (72) of the project. While Project Quality Management applies to allprojects, regardless of the nature of their product, product quality measuresand techniques are specific to the particular type of product produced by theproject.
A.performance
B.process
C.product
D.object
开始考试练习点击查看答案65● (73) is a category assigned to products or services having the samefunctional use but different technical characteristics. It is not same asquality.
A.Problem
B.Grade
C.Risk
D.Defect
开始考试练习点击查看答案66● Project (74) Management is the Knowledge Area that employs theprocesses required to ensure timely and appropriate generation, collection,distribution, storage, retrieval, and ultimate disposition of projectinformation.
A.Integration
B.Time
C.Planning
D.Communication
开始考试练习点击查看答案67● The (75) process analyzes the effect of risk events and assigns anumerical rating to those risks.
A.Risk Identification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring and Control
开始考试练习点击查看答案