A.4 weeks
B.5 weeks
C.6 weeks
D.7 weeks
E.None of the above.
A.Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).
B.Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.
C.The skill level of the added resources might not be appropriate for the activities to be performe
D.D.Adding more resources may create additional work and produce inefficiencies (i.
E., additional people may need training and supervision.)E.All of the above.
开始考试点击查看答案A.The project manager and project office personnel.
B.The project team and functional managers.
C.The project sponsor.
D.All of the abov
E.E.A and B.only.
开始考试点击查看答案A.Conceptual, execution.
B.Development, implementation.
C.Development, close-out.
D.Implementation, close-out.
E.Planning, finishing.
开始考试点击查看答案A.Now becomes the new schedule, including the changes, and the original baseline is disregarded.
B.Is still the original baseline but annotated to reflect that a change has taken place.
C.Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
D.B.Is still the original baseline but annotated to reflect that a change has taken plac
E.C.Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.D.Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)E.Is the same since baseline schedules cannot change once the development phase is completed.
开始考试点击查看答案A.This is a valid representation if the logic is correct.
B.This is invalid because a node can have a maximum of one dummy input representation if the logic is correct.
C.This is invalid because nodes cannot have both dummy inputs and dummy outputs.
D.This is a invalid because the number of outputs must equal the number of inputs.
E.This is invalid because a maximum of two inputs and two outputs are allowed using the critical path method.
开始考试点击查看答案A.All activities.
B.Only those activities with the longest time durations.
C.Those activities on the critical path begining with the longest time duration activities.
D.Those activities with the greatest degree of risk.
E.None of the above.
开始考试点击查看答案A.A shortening of the critical path.
B.A shortening of the noncritical path.
C.A decrease in the total cost of the project.
D.An increase in the cost of the project.
E.A through D are possible based upon where the resources are deployed.
开始考试点击查看答案A.Comparing actual to planned performance to each activity.
B.Showing slack time.
C.Showing critical path dependencies.
D.Showing which activities can be rearranged in parallel.
E.All of the above.
开始考试点击查看答案A.The critical path is also reduced.
B.The slack in the path containing this activity will increase.
C.The total cost for this activity has decrease
D.B.The slack in the path containing this activity will increas
E.C.The total cost for this activity has decreased.D.Manpower from this activity can be assigned to other activities.E.All of the above.
开始考试点击查看答案A.Slack for each activity, critical path.
B.Slack for each activity, high risk activities.
C.Manpower shortages, high risk activities.
D.High risk activities, non-critical paths.
E.Manpower availability, contingency plans.
开始考试点击查看答案房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它长理培训客户端 资讯,试题,视频一手掌握
去 App Store 免费下载 iOS 客户端