项目管理师PMP美国项目管理PMPPMP认证考试练习题(29,30)
题目内容

Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. This will provide information on the (    ) and identification of the (    ) .

2024-07-09

A.Slack for each activity, critical path.

B.Slack for each activity, high risk activities.

C.Manpower shortages, high risk activities.

D.High risk activities, non-critical paths.

E.Manpower availability, contingency plans.

题目答案

试卷相关题目

最新试卷
热门试卷

长理培训客户端 资讯,试题,视频一手掌握

去 App Store 免费下载 iOS 客户端