● (73) is a method used in Critical Path Methodology for constructing a projectschedule network diagram that uses boxes or rectangles, referred to as nodes, to representactivities and connects them with arrows that show the logical relationships that exist betweenthem.

2024-07-09

A.PERT

B.AOA

C.WBS

D.PDM

题目答案