题目内容

during a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12%of the work scheduled to this point of time. you can therefore conclude that:

2024-07-09

A.the project will be completed late.

B.the critical path has been lengthened.

C.the costs are being overrun.

D.C.the costs are being overrun.D.overtime will be required to maintain the original critical path.

E.none of the above.