项目管理师PMP美国项目管理PMPPMP认证考试练习题(11,12)
题目内容

once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the network. this willprovide information on the (    ) and identification of the (    ) .

2024-07-09

A.slack for each activity, critical path.

B.slack for each activity, high risk activities.

C.manpower shortages, high risk activities.

D.high risk activities, non-critical paths.

E.manpower availability, contingency plans.