assume that you have a network where an activity on the critical path can be crashed by two weeks. if the activity is actually crashed by twoweeks, then:

2024-07-09

A.the project's schedule will be reduced by 2 weeks.

B.the available slack on the noncritical paths will increase.

C.a new critical path may appear after the crash.

D.all of the abov