Documented work authorization provide:

2024-07-09

A.a means of effective internal coordination of the project's activities.

B.an audit trail of all work authorized from project initiation to completion.

C.a means for communication of work activity between the project manager and the performing activities.

D.All of the above

E.A and B only.

题目答案