项目管理师PMP美国项目管理PMPPMP认证考试练习题(27,28)
题目内容

Including the customer in the process of project planning is:

2024-07-09

A.Slow and counterproductive.

B.Essential in the definition and documentation of project goals.

C.Necessary, but of limited value.

D.Unnecessary because project goals are defined in the proposal stag

E.E.None of the above.

题目答案

试卷相关题目

最新试卷
热门试卷

长理培训客户端 资讯,试题,视频一手掌握

去 App Store 免费下载 iOS 客户端