项目管理师PMP美国项目管理PMPPMP认证考试练习题(27,28)
题目内容

Resource leveling (    ).

2024-07-09

A.Allocates resources to activities to find shortest schedule within fixed resource limits.

B.Smoothes out resource requirements by rescheduling activities within their float time.

C.Smooths out resource requirements by substituting activities with unassigned resources.

D.Attempts to reduce resource requirements within a constraint on project duration

E.B or D.