A.The late start date is earlier than the early start date.
B.The critical path supports the imposed end date.
C.The early finish date is equal to the late finish date.
D.When leads are employed in the schedul
E.E.The project is sinking.
A.Engineering
B.Marketing
C.Manufacturing
D.Accounting
E.Contracts and procurement
开始考试点击查看答案A.Immediately inform the sponsor and ask for advice
B.Do nothing until the slippage occurs
C.See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis
D.Look for someone to blame before you see the sponsor
E.Inform your senior management of the problem and tell them that you will get back to them after you assessed the situation
开始考试点击查看答案A.rearranging conflicting tasks
B.depicting actual versus planned tasks
C.showing the outer dependencies of tasks
D.A and C.
E.A and D.
开始考试点击查看答案A.A program is made up of multiple projects
B.A program requires at least three times longer to plan than a project
C.A project is a one-shot deal while a program is on-going
D.A and C.
E.B and C.
开始考试点击查看答案A.Discretionay dependencies
B.External depenencies
C.Mandatory dependencies
D.All of the above
E.A and B only
开始考试点击查看答案A.Start to Start.
B.Finish to Finish.
C.Start to Finish.
D.Finish to Start.
E.Dummy activity.
开始考试点击查看答案A.subtracting the end date of task one from the start date of task two.
B.determining which tasks have the least amount of total slack.
C.totaling the time for all activities.
D.determining the shortest path through the network.
E.Determining which tasks have the most slack
开始考试点击查看答案A.dig hole
B.remove debris
C.survey
D.set forms
E.place concrete
开始考试点击查看答案A.Fast tracking.
B.Crashing
C.Releasing resources earlier from tasks which were scheduled with a late start.
D.Alter to task priorities.
E.A or B.
开始考试点击查看答案A.Allocates resources to activities to find shortest schedule within fixed resource limits.
B.Smoothes out resource requirements by rescheduling activities within their float time.
C.Smooths out resource requirements by substituting activities with unassigned resources.
D.Attempts to reduce resource requirements within a constraint on project duration
E.B or D.
开始考试点击查看答案房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它房地产经纪人房地产经纪人房地产经纪相关知识2009年房地产经
类别:建筑类其它长理培训客户端 资讯,试题,视频一手掌握
去 App Store 免费下载 iOS 客户端