a variance envelope has been established on a project. the envelope goes from +-30% in r&d to +-5% during manufacturing. the reason forthe change in thickness of the envelope is because:

2024-07-09

A.the management reserve has been used up.

B.the accuracy of the estimates in manufacturing are worse than the estimates in r &

C.tighter controls are always needed as a project begins to wind down.

D.of the personal desires of the project sponsor.

E.of none of the above