项目管理师PMP美国项目管理PMPPMP认证考试练习题(11,12)
题目内容

a network has been developed with resources from six different departments. one of the six departments has just informed you that they canincrease the number of employees from 5 to 8. this will result in:

2024-07-09

A.a shortening of the critical path.

B.a shortening of the noncritical path.

C.a decrease in the total cost of the project.

D.an increase in the cost of the project.

E.a through d are possible based upon where the resources are deployed.

题目答案

试卷相关题目