increasing resources on the critical path activities may not always shorten the length of the project because:

2024-07-09

A.certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).

B.safety, osha and epa may have placed restrictions on the number of people used on certain activities or in the physical location of theproject.

C.the skill level of the added resources might not be appropriate for the activities to be performe

D.D.adding more resources may create additional work and produce inefficiencies (i.

E., additional people may need training and supervision.)E.all of the above.