during project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. the baselineschedule:

2024-07-09

A.now becomes the new schedule, including the changes, and the original baseline is disregarded.

B.is still the original baseline but annotated to reflect that a change has taken place.

C.is amended to reflect the scope change, but the original baseline is still maintained for post-project review.

D.B.is still the original baseline but annotated to reflect that a change has taken plac

E.C.is amended to reflect the scope change, but the original baseline is still maintained for post-project review.D.is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)E.is the same since baseline schedules cannot change once the development phase is completed.