the budgeted cost of the work performed (bcwp) for a task that has just been completed can be calculated by:

2024-07-09

A.multiplying the actual hours worked on the project by the budgeted labor rate.

B.multiplying the budgeted hours to complete the task by the budgeted labor rate.

C.dividing the actual hours required to complete the task by the budgeted labor rate.

D.cannot be determined.

E.none of the above