amount at stake is the (    ) .

2024-07-09

A.function of planned time/real time project costs.

B.risk identified in successful project completions.

C.(standard project deviation + expected costs)/6

D.cost of investment loss + least cost to restore status quo.

E.inherent risk at conception altered by standard project deviations.