题目内容

the identification, definition, and selection of the project objectives as well as the best approach to achieving the project objectives areindentified in the (    ) phase of the project but first documented in the project (    ).

2024-07-09

A.conceptual, charter/baseline.

B.conceptual, master schedule.

C.development, charter/baseline.

D.development, master schedul

E.E.development, masterplan.