there are two major types of reserves used on projects. the (    ) is for (usually major) scope changes that were not considered as part ofthe original plan, whereas the (    ) is to compensate for minor changes in estimating, escalation factors.

2024-07-09

A.management reserve, unplanned allowance fund.

B.management reserve, contingency.

C.contingency fund, management reserve.

D.B.management reserve, contingency.C.contingency fund, management reserv

E.D.unplanned allowance fund, budgetary reserve.E.unplanned reserve, planned reserve.