A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:

2024-07-09

A.Change the scope baseline

B.Prepare a variance report

C.Call a meeting of the configuration control board

D.Change the project's objectives

E.Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

题目答案